The City of Edinburgh Council is the
local authority charged with providing basic amenities and services for the
440,000 residents of the city (The City of Edinburgh Council, 2014). These
services range from transportation services, parking, healthcare, sanitation,
recycling, and education among others. Of relevance to this implementation is
the transportation function where the council takes measures to ensure that
people can move from one section of the city to the other with ease. It does
this by facilitating investment into the public transportation sector and
sponsoring and implementing projects such as the Trams project. This increases
speed, reliability, and cost effectiveness of the transportation systems (Audit
Scotland, 2011). It also focuses on limiting the level of environmental
degradation arising from operations in the transportation sector. These
services provide a wholesome impact of improving the quality of life and
promoting economic, social and environmental sustainability.
The Edinburgh Tram Project was conceived
in 2003 and endorsed by the Scottish government in 2007 (The City of Edinburgh
Council, 2014). It aimed at improving public transportation within the city of
Edinburgh. It also aimed at growing the local economy while creating a healthy,
safe and sustainable environment within the city. It entailed the construction
of tram lines at different parts of the city as shown in the figure below.
The project was cost conceived in 2003 and estimated to cost £375 million. However, subsequent revisions of the project had the budget revised to £776 million (Audit Scotland, 2011). This was double the initial estimate. There were also delays with the project completion being pushed from 2011 to 2014. In spite of the delays, the building of the project infrastructure was completed in October 2013 with testing ongoing pending the projected project launch in May 2014.
The project implementation was initially
spearheaded by Transport Initiatives Edinburgh (TIE), a wholly owned subsidiary
of the City of Edinburgh Council (Edinburgh Trams, 2014). The company was
registered to shield the Council from liabilities related to the running of the
project. TIE was the overall manager of the project and was tasked with the
responsibility of contracting suppliers to cater for sections of the contract.
For instance, the operation of the trams was initially contracted to Transdev.
This was cancelled in December 2009 and awarded to Edinburgh Trams Limited
(Audit Scotland, 2011). The main player in building the tram system was BBS.
This was a consortium of three companies including Bilfinger Berger, Siemens
and Construcciones y Auxiliar de Ferrocarriles.
Contractual disputes arose between BBS and
TIE leading to a delay in the implementation of the project. Funding challenges
were also experienced prompting the council to shorten the length of the line. On
the whole, the level of success in the project implementation was low when
gauged against budgetary considerations, timelines, and the level of
collaboration between the main stakeholders.
The key stakeholders were as follows:
- City of
Edinburgh Council CEC: The owner of the project
- Transport
Initiatives Edinburgh (TIE): The project manager, a private company wholly
owned by CEC
- Tram
operator: This role was initially given to Transdev but was later awarded
to Edinburgh Trams Limited
- Infrastructure
contractor: This was done by BBS, a consortium of three companies
including Bilfinger Berger, Siemens and Construcciones y Auxiliar de
Ferrocarriles
- Utility
diversion contractor: Alfred McAlpine Infrastructure Services was awarded
this contract in October 2006 and completed its work by November 2009
- Tram
constructor: Apart from being a member of the BBS consortium,
Construcciones y Auxiliar de Ferrocarriles SA (CAF) was awarded the
contract to develop trams and deliver them to them in time for the testing
of the project (Audit Scotland, 2011). BBS was also responsible for
overseeing the activities of Parsons Brinkerhoff to the Systems Design
Service (SDS) which was responsible for installing overhead power lines
and electronic systems.
The aims of the Edinburgh Tram Project
were as listed below:
- To boost
the city’s economy by facilitating access
- To reduce
the level of environmental harm caused by traffic by establishing a
transportation system that doesn’t produce carbon emissions
- To reduce
traffic congestion by providing a viable alternative to the use of vehicles
for city dwellers moving around the city
- To promote
safety and security in the transport sector
- To promote
social benefits
The Edinburgh Tram Project was first
conceptualised in 2001 and the Transport Initiatives Edinburgh (TIE) formed as
a wholly owned subsidiary in of the City of Edinburgh Council in May 2002 (The
City of Edinburgh Council, 2014a). TIE was charged with the responsibility to
investigate into how best to deliver the Council’s local transport strategy. It
would also be in charge of overseeing implementation the project including contracting
suppliers, paying suppliers, and ensuring that quality standards are upheld in
the process of implementation (Edinburgh Trams, 2014). This arrangement of
letting a private company oversee the project was intended to insulate the
project from politics, and also shift the risks involved from the council to
the private sector. TIE was responsible for the Edinburgh Tram Project until
August 2011.
The plan produced comprised of two
phases: 1a and 1b. 1a was planned to include an 18.5km line stretching from
Newhaven, through Princes Street, to Edinburgh Airport (BBC News, 2013). 1b was
planned to cover 5.6km running from Haymarket, through Crewe Toll, to Granton
Square. The second phase 1b was cancelled in 2009 due to the economic
difficulties faced by the country at the time. The project was consented to in
December 2007.
The project was divided into the
following sections, each of which was contracted to a different supplier:
- Project
design: This included drawings for all the infrastructure needed,
coordinating the purchase of the land needed, and alignment with the
existing traffic regulations
- Utilities
diversion works and other enabling works: This included the construction
of a park and ride at Ingston.
- Infrastructure
construction (Infraco): This would be the core of the project. It would
include the construction of the tramlines and tram depot. It would also
include procurement and installation of ticketing machines, construction
of passenger shelters, and the installation of overhead power lines. This
is because the trams would be powered using electricity.
- Construction
of 27 trams (Tramco). This would need to be completed in time for testing
prior to the official launch of the projects.
The cost of the project was estimated at
£375 million in 2003. The Scottish government set an upper limit for the
project at £500 million noting that if the cost exceeded £545 million, it would
cost more than the projected benefits (Audit Scotland, 2011). The budget was,
however, revised several times with the final estimated cost being at £776
million.
The project was projected to provide
benefits of 231% over the cost of the project. It would include the
construction of 3800 residential units, 930 jobs (530 attributed to phase 1a),
improved quality of air, low noise levels, and improved access to key sections
of the city.
The project timeline was estimated at
3years running from 2008 to 2011. It was expected that the trams transportation
system would be operational by February 2011. However, delays in the project
implementation led to several revisions with the current projection being for
the project to be launched by May 2014.
The project timelines and milestones are
shown in the figure below:
Budgetary uncertainties were among the
risks anticipated in planning the project. These were reduced by early award of
the design contracts. This would facilitate an early conception of the project
and accuracy in cost estimation.
The utilities’ infrastructure in the
city was viewed as a potential risk to timely execution of the project. This
would be due to the need to relocate certain utilities to ensure that the
delivery of services to the city is not interrupted (The Guardian News, 2014).
To avoid this risk, utility diversion was conceived as a separate contract to
ensure that the project is not delayed.
The other risk anticipated was related
to the likelihood of suppliers delivering unevenly on services concentrating on
their core strengths. This risk is very likely where one supplier handles a
wide range of services in projects. This risk was minimised by separating core
elements of the project where infrastructure construction and development of
trams were separated.
The separation of the contracts was
nevertheless limited to reduce the risk associated with coordination weaknesses
(Audit Scotland, 2011). The entire contract for infrastructure development was
handed to the BBS consortium. This was done to promote coordination of the
complex aspects of the project and reduce the risks associated with poor
coordination between different organisations.
Cost fluctuations were also anticipated.
Cost fluctuations can be very risky as they could not only affect the
affordability of the project, but also make the costs higher than the benefits.
This was a real concern, considering that the project approval was tagged to
the assurance that the project would not exceed a specific budgetary
allocation. TIE sought to minimise this risk by seeking to make the contract
amounts fixed. The commitment was evident in the provision of compensation
mechanisms in case part of the project was not implemented. For instance, £3.2
million demobilisation fee was to be paid in the event that phase 1b of the
project failed to kick off.
The likelihood of disputes between
suppliers and TIE was also anticipated with the potential impact of paralysing
the project. TIE sought to minimise the likelihood and impact of this risk by
providing mechanisms for mediation in the contracts. Disagreements would
therefore be mediated first before any legal action is taken. As a result,
project implementation would be guaranteed to continue with little or no
interruptions.
None of the projections at the planning
phase were achieved. By December 2010, only 28% of the project had been
completed making it unrealistic to expect the launch to be in February 2011 as
earlier projected.
Despite the initial budget of £375
million in 2003, the council had already spent £402 million in by December 2010
when only 28% of the project had been completed. The projection at the time was
that £545 million would be sufficient to complete the project. However, 2014
estimates are that the project has cost a total of £776 million. This is double
the initial estimate, displaying serious flaws in budgeting and actual
implementation.
Being a government project, the Tram
Project has come under intense scrutiny and at times fought based on party
manifestos alone. For instance, the Scottish National Party included the
project in its manifesto as one of the unnecessary projects that it would scrap
in its bid to save public resources. Questions on the cost of the project were
raised with accusations of mismanagement being high. This prompted the
appointment of an auditor to determine the extent to which the project has
delivered value for money. The pressure is expected to have dampened public
support for the project. Pressure from lobby groups such as the cyclist
associations had the impact of shedding a dark shadow on the project. The
cyclists decried the fact that their bicycles would frequently be caught up in
the tram lines, often leading to injury. This led to a commitment to repair
roads for the cyclists to use; further complicating the project.
The legal dispute between TIE and BBS
has been the main cause of delay for the project. In this dispute, BBS demanded
compensation for design changes brought about by incomplete utility diversion
works in part of the sections. This compensation demand was for £50-80 million
(Audit Scotland, 2011). TIE dismissed this claim as unsubstantiated causing a
delay of the project pending resolution of the matter. A project management
panel was constituted in June 2009 to try and mediate on the fallout with
failure of the talks leading to a legal suit. The disagreements were bad enough
to get TIE to consider terminating the contract. The project stalled for the
duration of the legal dispute hence causing a serious delay on the project
timelines. By December 2010, it was estimated that the new deadline for the
project would be February 2013. This was later revised to May 2014 (BBC News,
2013).
Funding challenges were also
experienced. This was related to the frequent budgetary adjustments that went
beyond the limits recommended by the Scottish government. An upper limit had
been set at £545 million. However, by June 2010, the project cost estimate had
been raised to £600 million. The extra £55 million would be met by either
borrowing funds or reducing the length of the tram lines being constructed
(Audit Scotland, 2011). The option of truncating the line was picked to reduce
the cost estimates. However, costs would further be raised as a result of TIE
being disbanded in late 2011 with consultants Turner & Townsend taking over
the management of the project. The new cost estimates were revised to £770
million with the council voting to truncate the line further to save on the
cost of the project.
The project scope was revised several
times. In 2009, phase 1b was cancelled due to the financial crisis that made
funding difficult. In June 2010, budget constraints led to the council seeking
proposals on the cost savings that would be made if the tram line was truncated
in 4 different points including the Haymarket station and York Place. The
decision to truncate the Haymarket station was made in June 2011 with an impact
of reducing the budgetary estimate by £72 million. This means that the final
project is much shorter than and twice as expensive as initially planned.
The problem was faced with several
problems related to quality and failure to meet deadlines. By May 2008, the
company was yet to complete design for parts of the sections making it
difficult for the infrastructure construction designs to be completed. These
delays had the impact of delaying the whole project because of the interconnectedness
of the different project phases. For instance, Parsons Brinkerhoff to the
Systems Design Service (SDS) was found to be very inefficient in resource
mobilisation leading to delays in delivery of electronic systems and overhead
power lines (Audit Scotland, 2011). This delayed the process of infrastructure
construction. Moreover, quality problems identified warranted revision of the
work hence causing further delay of the project.
Another crucial delay was occasioned by
poor quality in delivery of the utility transfer function. After failing to
execute on its mandate on ensuring completion of utility transfer, the
infrastructure developer was forced to redesign its infrastructure at an
additional cost prompting them to seek compensation. This led to the long legal
suit that is credited for the long delay of the project.
The current status of the project is
that infrastructure construction is complete. The trams have also been
delivered and all systems in place. Testing is expected to be ongoing pending
the official launch of the system in May 2014 (BBC News, 2013).
A number of risks can be anticipated
that could lead to further delay and additional expenditure on the project. This
can happen upon discovery of quality hitches leading to revision of sections of
the work. For instance, a section of the tramline is already observed to have
cracks (McCann, 2014). The likelihood of this risk occurring is relatively high
considering the fact that the project has been marred with quality hitches in
the course of the implementation. The necessity of revisions cannot be
overruled as failure to facilitate them could lead to the trams transportation
system being risky for the passengers. However, revisions do not necessarily
need to lead to delay of the launch. Minor changes can be conducted while the
system is operational. It is unlikely that large quality issues warranting
substantial delays would be discovered given that inspection must have been
conducted thoroughly before infrastructure development was declared as complete
in October 2013.
Risk of budgetary allocations being
inadequate is also high. The impact of such a risk is likely to be low as it is
not expected that the council would entertain the idea of aborting the project
after the far it has come with it. However, this would further complicate
issues surrounding it. Given that each part of the project was contracted to
specific suppliers, the council would only need to hold those responsible to
account and require that revisions of work be conducted at their own costs.
Where legal hurdles are encountered, the council can fund the revisions while
pursuing a legal process for compensation of the amounts incurred.
The system is designed for use by
members of the public. It would be futile if such a system is launched and
members of the public opt to maintain their lifestyles in terms of the
transportation modes that they prefer. This calls for public awareness and
marketing campaigns aimed at making the system more acceptable. In this regard,
there is already a delay as little has been done to procure public support for
the new system of public transportation. While it may be rational to assume
that the public would quickly embrace a faster means of transport that would
enable them beat the traffic congestion, it would be necessary for a publicity
campaign to be conducted to weaken the level of attachment that people have
with their cars and approach to transportation. This is more likely considering
that the trams project only covers a limited length within the city and people
may not be at ease letting go of their cars just yet.
As has been discussed earlier in this
report, the project was initially commissioned to Transport Initiatives
Edinburgh (TIE) and later to consultants Turner & Townsend. These private
companies would oversee implementation and contract suppliers to work on
different parts/stages of the project. The project model was to insulate the
City of Edinburgh Council from liabilities arising from the project, and also
to insulate the project from partisan politics as would be characteristic of
government-related projects.
The planned design was to create
certainty in the budget and implementation. These were not achieved with the
project being delayed by over 3 years and the budget being more than twice the
initial budget.
The project balanced between the need to
have suppliers deliver on their areas of specialty and the need to have
projects coordinated with ease. This is why the project was broken down into
stages with different contracts being made with specific suppliers. To aid
coordination, BBS, the developer of infrastructure, was made to oversee
elements such as the development of power lines and electronic systems.
Measures to reduce budgetary
uncertainties included negotiating for fixed project cost amounts. This was
arguably achieved. The legal dispute with BBS was related to compensation for a
job not done by a different contractor, and not a revision of their contractual
fees. This was the argument that led to them being awarded the compensation in
the protracted legal battle initiated by TIE. The presence of the legal dispute
also means that the mediation mechanisms established to eliminate the risk of
delay did not bear the desired fruit. It was after the project management panel
failed that the acrimonious court battle began.
The project was characterised by delays
related to poor quality warranting revision of work and a legal dispute with
the main supplier BBS. The details of
the delays differed with estimates for time of completion being revised in 2010
to February 2013 and later to May 2014 (Audit Scotland, 2011). The construction
of infrastructure was finally completed in October 2013 pending project launch
in May 2014.
As was the case with the budget and
timeline projections, the scope of the project was revised several times. From
the cancellation of phase 1b of the project to truncation of several parts of
the line, the final project was significantly different from the anticipated
project. This has the impact of making it difficult to estimate the benefits of
the project in terms of the economic and social benefits in the absence of new
research.
Instead of being involved in supervising
every aspect of the project, a better project model would have been to make the
main supplier responsible for the whole project. This would have helped to
ensure that the cost estimates are final and that there are no justifiable
reasons for demanding an increase on the cost of the project.
The aims targeted using this project
design would still be achievable in the all-inclusive project contracts
recommended. The process of prequalification or evaluation would include
gauging the competence of the main supplier and that of the sub-contractors
responsible for handling different aspects of the project.
It is anticipated that this project will
be launched in May 2014. However, possible risks related to discovery of
quality issues warranting revisions are likely. There is also the risk of the
new transportation system to attract little public support due to its scope and
the extent to which the public may be attached to their current lifestyles.
This makes it necessary to invest in publicity and get city residents to leave
their vehicles to use the tram systems.
Audit Scotland, 2011. Edinburgh Trams: Interim Report. (Online) Available at:
http://www.audit-scotland.gov.uk/docs/central/2010/nr_110202_trams.pdf
(Accessed 27 April 2014)
BBC News, 2013. Edinburgh
trams: Services 'will be running by next May'. (Online) Available at:
http://www.bbc.com/news/uk-scotland-edinburgh-east-fife-24124047 (Accessed 27
April 2014)
Edinburgh Trams, 2014. Our Trams. (Online) Available at: http://www.edinburghtrams.com/
(Accessed 27 April 2014)
McCann, D., 2014. Cracks appear on Shandwick Place tram route. (Online) Available at:
http://www.edinburghnews.scotsman.com/news/transport/cracks-appear-on-shandwick-place-tram-route-1-3374224
(Accessed 27 April 2014)
Prior, G., 2014. Edinburgh
Trams testing to go daily. (Online) Available at:
http://www.britishtramsonline.co.uk/news/?cat=11 (Accessed 27 April 2014)
The City of Edinburgh Council, 2014. Trams. (Online) Available at:
http://www.edinburgh.gov.uk/trams/ (Accessed 27 April 2014)
The City of Edinburgh Council, 2014a. The Tram Project. (Online) Available at:
http://www.edinburgh.gov.uk/info/20126/trams/177/the_tram_project (Accessed 27
April 2014)
The Guardian News, 2014. Edinburgh trams: The story so far. (Online) Available at:
http://www.theguardian.com/edinburgh/2010/jun/23/edinburgh-trams-timeline-facts-tram-latest-transport
(Accessed 27 April 2014)
Ford, D.N., Bhargav, S., 2006. Project management
quality and the value of flexible strategies. Engineering, Construction and Architectural Management, 13(3), pp.
275-289
Harin, E., 2007. Project
management in the real world. Swindon: The British Computer Society
Harrington, R.J., Ottenbacher, M.C., 2011. Strategic
management. International Journal of
Contemporary Hospitality Management, 23(4), pp. 439-462
Horine, G., 2013. Project management: absolute beginner's guide. 3rd Ed. Horine
Indianapolis, IN: Que
Jugdev, K., Mathur, G., 2006. Project management
elements as strategic assets: preliminary findings. Management Research News, 29(1), pp. 604-617
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and
controlling. New York: Senior Executive Director for Project Management,
the International Institute for Learning
Larson, E.W., 2011.
Project management: the managerial
process. 5th Ed. New York : McGraw-Hill Irwin
Lyle, M.A., 2013. Total Quality Management. Quality, 52(2), pp. 40-42
Nice blog! I read your article. I really like all the points that you mentioned are interesting and helpful. Thank you for sharing this blog.
ReplyDeletecirencester transports UK
I wrote about a similar issue, I give you the link to my site. Project Management Services
ReplyDeleteI trust you post again soon... 4th Hokage Coat
ReplyDeleteNice and interesting post, I appreciate your hard work, keep uploading more, Thank you for sharing valuable information. streetwearapparels.com
ReplyDeleteIts an interesting and useful information. We all get highly motivation from this .
ReplyDeleteshophoodies.co.uk
The blog was informative! Finding the right real estate agent in Toronto can be a tricky task. There are so many agents to choose from, and it can be difficult to know who to trust. With so much at stake, you need to make sure that you find an agent who is knowledgeable and experienced in the Toronto real estate market.
ReplyDeleteproject management consultancy