Risk
= Probability x Impact
Establish
a scale that reflects the perceived likelihood
–
Probability scales are commonly used
– Can
be qualitative or quantitative
e.g.
highly improbable, improbably, moderate, likely,
highly likely
0-100%
probability
Risk
= Probability x Impact
Three
factors can be used to assess impact of the risk:
–
Nature
– Scope
–
Timing of the risk
Risk Handling
Risk avoidance
Risk containment
Risk reduction and risk prevention
Risk mitigation
Risk Monitoring
e.g., when certain milestones are reached
Useful
to regularly assess and update project risk exposure
Senior management should be involved in monitoring and
should be aware of exposures
Listen to the project group
Risk and Contingency Planning
Technical Risks
¡ Backup strategies if chosen
technology fails.
¡ Assessing whether technical
uncertainties
can be resolved.
can be resolved.
Schedule Risks
¡ Use of slack increases the risk of a
late project finish.
¡ Imposed duration dates (absolute
project finish date)
¡ Compression of project schedules due
to a shortened project duration date.
Costs of Risks
¡ Time/cost dependency links: costs
increase when problems take longer to solve than expected.
¡ Deciding to use the schedule to
solve cash flow problems should be avoided.
¡ Price protection risks (a rise in
input costs) increase if the duration of a project is increased.
Funding Risks
Changes in
the supply of funds for the project can dramatically affect the likelihood of
implementation or successful completion of a project.
Contingency Funding and Time Buffers
Contingency Funds
¡
¡ Budget reserves
¡ Management reserves
Time Buffers
Amounts of
time used to compensate for unplanned delays in the project schedule.
Managing Risk: Step 4: Risk Response Control
Design Appropriate Responses to the Risk
} Ignore
or accept the risk
} Reduce
the probability of the risk
} Reduce
or limit the consequences
} Transfer,
share or deflect the risk
} Make
contingency
} Adapt
to it
} Oppose
a change
} Move
to another environment
Unknowable Risks
Even
when reasonable forecasts are made, analysis carried out, etc the future is
unpredictable and there will still be unforeseen events:
¡ 1
Inherently unknowable risks eg fire
÷ Use
Business Continuity Mgt
¡ 2 Time dependent risk eg cannot say
what will happen next year
3 progress-dependent risks eg
introducing lean operations, risks will only appear after implementation
4 response-dependent risks:
secondary risks eg responding to material shortages will leave company open to
risk from unknown supplier
So:
Use
formal procedures for risk identification, AND regular reviews to minimise
surprises..
No comments:
Post a Comment